溧阳抽水蓄能电站主体工程土石方调配平衡研究 被引量:1

Study on allocation balance of earth-rock work for main works of Liyang Pumped Storage Hydropower Station
下载PDF
导出
摘要 针对溧阳抽水蓄能电站工程C1标、C2标的施工方案,较全面系统地分析了土石方施工工程中的影响因素,以及各个方面相互联系和制约关系,进行了土石方调配平衡系统与道路运输系统等的综合优化,以寻求合理的土石方调配方案,达到快速、合理、经济施工之目的。 In allusion to the construction schemes of the bid-sections of CI and C2 of the construction of Liyang Pumped Storage Hydropower Station, the impact factors from the construction of the earth-rock work are systematically analyzed herein along with the study on the mutually associated and restricted relationships at all the aspects concerned, and then the comprehensive optimizations are made on both the balancing system for the allocation of the earth-rock work and the road transportation system, so as to obtain a reasonable earth-rock work allocation scheme and get the target of quick, reasonable and economic construction.
出处 《水利水电技术》 CSCD 北大核心 2011年第7期56-59,共4页 Water Resources and Hydropower Engineering
关键词 溧阳抽水蓄能电站 土石方工程 调配 综合优化 Liyang Pumped Storage Hydropower Station earth-rock work allocation comprehensive optimization
  • 相关文献

参考文献3

二级参考文献43

共引文献51

同被引文献8

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部