摘要
沙湾电站地质条件复杂,厂房基础固结灌浆对厂房的安全有重要影响。本文对厂房基础固结灌浆施工及施工中遇到的技术难题及解决办法进行了阐述。
The consolidation grouting for the powerhouse foundation of Shawan Hydropower Station is very important for the safety of the powerhouse, as the geological condition therein is quite complicated. The construction of the consolidation grouting for the powerhouse foundation and the technical problems during the construction as well as their solving methods are expatiated herein.
出处
《水利水电技术》
CSCD
北大核心
2011年第7期64-66,70,共4页
Water Resources and Hydropower Engineering
关键词
沙湾水电站
固结灌浆
施工技术
厂房基础
Shawan Hydropower Station
consolidation grouting
construction technology
powerhouse foundation