结合某电厂过海电缆隧道工程,详细介绍了气压法施工的气压系统、气闸墙及人行闸结构气压"的设定、气压施工工艺、安全措施以及施工的效果。
Combined with the construction of a cross-sea cable tunnel project of a power plant,the paper introduces the usage of compressed air in shield tunnel construction,including the pneumatic system,structures of air lock wall and manlock,setting of air pressure value,construction techniques,security measures and construction effects.
出处
《地下工程与隧道》
2011年第2期25-27,30,共4页
Underground Engineering and Tunnels