一种求解RCPSP的协同进化分布估计算法 被引量:1

Coevolutionary Estimation of Distribution Algorithm for Solving Resource-constrained Project Scheduling Problem
下载PDF
导出
摘要 针对大规模资源受限项目调度问题计算复杂的特点,提出一种合作式协同进化分布估计算法(CCEDA)。将合作式协同进化框架与分布估计算法相结合,将复杂问题分解为子问题,利用改进的分布估计算法对每个子问题进行协同优化求解。为提高分布估计算法的局部搜索能力,给出一种对解进行局部搜索的方法。将CCEDA用于求解标准问题库PSPLIB,并与GAPS、GA-DBH、GA-hybrid与GA-FBI算法进行比较,结果证明CCEDA拥有更好的求解性能。 This paper presents Cooperative Coevolutionary Estimation of Distribution Algorithm(CCEDA) to solve Resource-constrained Project Scheduling Problem(RCPSP).It integrates the cooperative co-evolutionary framework and Estimation of Distribution Algorithm(EDA),decomposes RCPSP into several sub-problems,and then applies improved EDA to cooperatively solve these sub-problems.In order to enhance the local search ability of EDA,it gives a local search method for solutions.CCEDA is compared with GAPS,GA-DBH,GA-hybrid and GA-FBI,and experimental results on PSPLIB prove that CCEDA has better performance.
出处 《计算机工程》 CAS CSCD 北大核心 2011年第14期134-136,共3页 Computer Engineering
基金 国家自然科学基金资助项目(60674078 50975039)
关键词 资源受限项目调度问题 项目调度 分解策略 协同进化 分布估计算法 合作式协同进化分布估计算法 Resource-constrained Project Scheduling Problem(RCPSP) project scheduling decomposition strategy coevolutionary Estimationof Distribution Algorithm(EDA) Cooperative Coevolutionary Estimation of Distribution Algorithm(CCEDA)
  • 相关文献

参考文献3

  • 1Kolisch R, Hartmann S. Experimental Investigation of Heuristics for Resource-constrained Project Scheduling: An Update[J]. European Journal of Operational Research, 2006, 174(1): 23-37.
  • 2Larranaga P, Lozano J. Estimation of Distribution Algorithms: A New Tool for Evolutionary Computation[M]. [S. 1.]: Kluwer Academic Public, 2002.
  • 3周铁军,李阳.Multi-Agent协同进化算法研究[J].计算机工程,2009,35(13):205-207. 被引量:8

二级参考文献5

  • 1Potter M A.The Design and Analysis of a Computational Model of Cooperative Coevolutionary[D].Fairfax County,Virginia,USA:George Mason University,1997.
  • 2Choi I C,Kim S I,Kim H S.A Genetic Algorithm with a Mixed Region Search for the Asymmetric Traveling Salesman Problem[J].Computers and Operations Research,2003,30(5):773-786.
  • 3Tsai H K,Yang J M,Tsai Y F,et al.An Evolutionary Algorithm for Large Traveling Salesman Problems[J].IEEE Transactions on Systems,Man,and Cybernetics,Part B:Cybernetics,2004,34(4):1718-1729.
  • 4Jun Ouyang,Yan Guirong.A Multi-group Ant Colony System Algorithm for TSP[C]//Proceedings of the 3rd International Conference on Machine Learning and Cybernetics.New York,USA:[s.n.],2004:117-121.
  • 5Dorigo M,Gambardella L M.Ant Colony System:A Cooperative Learning Approach to the Traveling Salesman Problem[J].IEEE Transactions on Evolutionary Computation,1997,1(1):1-26.

共引文献7

同被引文献12

  • 1Blazewicz J,Lenstra J K,Kan R. Scheduling Subject to Resource Constrains:Classification and Complexity[J].Discrete Applied Mathematics,1983,(01):11-24.
  • 2Kolisch R,Sprecher A,Drexl A. Characterization and Generation of General Class of Resource-constrained Project Scheduling Problems[J].Management Science,1995,(10):1693-1703.
  • 3Elmaghraby S E. Activity Networks:Project Planning and Control by Network Models[M].New York:John Wiley and Sons,Inc,1977.
  • 4Demeulemeester E,Herroelen W. A Branch-and-Bound Procedure for the Multiple Resource-constrained Project Scheduling Problem[J].Management Science,1992,(12):1803-1818.
  • 5Artigues C,Michelon P,Reusser S. Insertion Techniques for Static and Dynamic Resource-constrained Project Scheduling[J].European Journal of Operational Research,2003,(02):249-267.
  • 6Birbil S I,Fang S C. An Electromagnetism-like Mechanism for Global Optimization[J].Journal of Global Optimization,2003,(03):263-282.
  • 7Birbil S I,Fang S C. On the Convergence of a Populationbased Global Optimization Algorithm[J].Journal of Global Optimization,2004,(2-3):301-318.
  • 8Debels D,Reyck B D,Leus R. A Hybrid Scatter Search/Electromagnetism Meta-heuristic for Project Scheduling[J].European Journal of Operational Research,2006,(02):653-683.
  • 9Godinho P,Branco F G. Adaptive Policies for Multi-mode Project Scheduling Under Uncertainty[J].European Journal of Operational Research,2012,(03):553-562.
  • 10Kochetov Y,Stolyar A. Evolutionary Local Search with Variable Neighborhood for the Resource Constrained Project Scheduling Problem[A].Ufa,Russia:[s.n.],2003.

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部