摘要
南广铁路郁江特大桥主桥结构形式为(36m+96m+228m+96m+36m)双索面斜拉钢桁连续梁桥,钢梁架设方案原设计为从主墩对称向两侧架设钢梁,经过对工艺、工期、成本的综合论证,确定采用从边跨向中跨架设的方案。
The structural form of the main bridge of Yujiang River Bridge on Nanning-Guangzhou Railway is a cable-stayed bridge with double cable planes and with a 5 span continuous steel-truss girder(36 m+96 m+228 m+96 m+36 m),the original erection scheme is that steel-truss girders are symmetrically erected from the main pier to both sides,and through the comprehensive demonstration on process,construction period and cost,the final erection scheme is that the steel-truss girders are erected from side span to mid-span.
出处
《科技情报开发与经济》
2011年第19期212-214,共3页
Sci-Tech Information Development & Economy
关键词
钢桁斜拉桥
钢梁架设
方案优化
steel-truss cable-stayed bridge
steel girder erection
scheme optimization