建(构)筑物下盾构注浆加固开仓换刀施工技术 被引量:5

Floor Reinforcement and Replace Technique of Shield Cutter Teeth Under High-rise Building
下载PDF
导出
摘要 结合深圳地铁2号线2204标盾构项目,通过砂浆置换和超前小导管注浆加固地层,建立土仓内正面土压力平衡,并辅以地面沉降监测,利用监测数据指导施工,实现了常压下开仓换刀,对同类工程在常压下检查、更换刀具具有借鉴意义。 Based on construction of bid 2204 of Shenzhen metro line 2, use integral displaced with mortar and grouting with leading conduit to reinforce soil, this will establish soil pressure balance in front of cutter head, technician through land subsidence monitoring to get the monitoring data and use the data to guide construction, those methods realizes replacing of cutting teeth under atmospheric Pressure, the paper can be served as reference for similar cases in the future.
作者 胡军
出处 《科技信息》 2011年第21期313-314,共2页 Science & Technology Information
关键词 砂浆置换 超前小导管注浆 更换刀具 沉降监测 Displace with mortar Grouting with leading conduit Replacing of cutting teeth Subsidence monitoring
  • 相关文献

参考文献1

二级参考文献3

  • 1唐大雄 刘佑荣 张文殊 等.工程岩土学[M].北京:地质出版社,1999.6-77.
  • 2叶文麟,叶观宝.地基处理[M].北京:中国建筑工业出版社,1997.35-37.
  • 3龚晓南,张航.第四届地基处理学术讨论会论文集[C].浙江大学出版社,1995.

共引文献7

同被引文献33

引证文献5

二级引证文献33

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部