摘要
概述了对300MW机组锅炉PCV阀控制系统的改造过程,取消了PCV阀现场压力控制器,将PCV阀压力控制回路接入DCS控制系统,减少了故障点,增加了PCV阀控制系统的可靠性。
The paper summarizes the improvement process of the PCV valve control system of a 300MW unit boiler,removes PCV valve site pressure controller and connects PCV valve pressure control loop to DCS control system,reducing fault point and increasing reliability of PCV valve control system.
出处
《电气开关》
2011年第4期56-57,89,共3页
Electric Switchgear