软塑淤泥地层中继间顶进框架桥施工技术 被引量:7

Construction Technology of a Frame Bridge by Intermediate Relay Jacking in Soft Plastic Silt
下载PDF
导出
摘要 为了确保天津市塘沽区中心路下穿铁路编组场框架桥工程(11.5-11.5)m双孔框架桥顺利顶进,顶进段分3节,现浇段分2节,全桥总长120.781 m。针对该工程的施工重点及难点,提出了包括基坑周边施作止水帷幕,钻孔灌注桩围护基坑、坑内降水,软弱地层加固处理,采用中继间法顶进框架桥一整套施工技术方案,使软塑淤泥地层中继间顶进框架桥施工技术不断趋于完善。 In order to ensure the jacking of a two-span rigid frame bridge (11.5+11.5m) for the Center Road of Tanggu District in Tianjing city to under-pass the railway marshalling yard, the jacking section was divided into three sub-sections, with other two sections cast on site, the totall length of the bridge being 120. 781m. In view of the construction difficulties, a set of techniques were proposed, including: water-stop curtain around foundation pit, pit protected by bored in-situ cast piles, water-lowering inside pit, consolidation of soft plastic silt soils, intermediate relay jacking, etc. These perfected the jacking of rigid frame bridge to traverse soft silt.
作者 高玉兰
出处 《铁道标准设计》 北大核心 2011年第8期71-74,共4页 Railway Standard Design
关键词 框架桥 基坑围护 软基处理 中继间顶进 施工 Rigid frame bridge Foundation pit protection Treatment of soft foundation Intermediate relayjacking Construction
  • 相关文献

参考文献10

  • 1铁建设[2009]226号铁路工程施工组织设计指南[S].
  • 2京铁师[2010]249号关于公布《营业线施工安全管理实施细则补充办法》的通知[S].
  • 3铁道部工务局工桥[1998]2号既有繁忙干线桥梁改造暂行技术条件[S].
  • 4TBl0203-12002铁路桥涵施工规范[S].
  • 5TBl0002.5-2005铁路桥涵地基和基础设计规范[S].
  • 6铁道部第三勘察设计院.铁路工程设计技术手册《桥梁地基和基础》[M]北京:中国铁道出版社,1991.
  • 7刘正峰.地基与基础工程新技术实用手册[M].北京:海潮出版社,2006.
  • 8地基处理手册编写委员会地慕处理手册[M]北京:中国建筑工业出版社,1988.
  • 9TBl0002.1-2005,铁路桥涵设计基本规范[S].
  • 10TBl0002.4-2005铁路桥涵混凝土和砌体结构设计规范[S].

共引文献25

同被引文献45

引证文献7

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部