针对矿山传统采剥进度计划编制方式存在工作量大、效率低的缺点,在Surpac平台下利用Tcl/Scl语言开发了适用于露天矿的采剥进度计划系统,采用人机交互方式,输入开采参数制定采剥进度计划,效率高,能灵活地调整采剥计划方案;利用生产炮孔数据建立地质-采矿模型,提高了矿岩量及品位的计算精度,适用于各种类型的金属露天矿山开采。
According to the disadvantage of traditional stripping and mining scheduling formulation way for mine involving massive work and inefficiency,a stripping and mining scheduling system suit to open-pit mine was developed by using Tcl/Scl language based on Surpac.This system input mining parameters through the man-machine interactive way,and the stripping and mining scheduling which was efficient and could adjust schedule plan flexibly formulated.The computational accuracy of tonnage for ores and rocks and the grade could be improved based on geological-mining model which was established by utilize production blast hole data.The system could be used in different kinds of open-pit metal mines.