介绍了马钢新区钢轧系统电网接线方式及负荷情况,分析了钢轧系统电网维持孤网运行的可能性及不利因素,从机组调速系统优化、运行和调度措施等方面对孤网运行提出了设想和建议。
The connection mode and the load of the power grid at the newly-built area of Maanshan Iron Steel Co.,Ltd.are presented.The probability and disadvantages of the isolated power grid operation for steel making and rolling system are analyzed.The assumption and suggestion on the isolated power grid operation are offered from optimization,operation of speed governing system of the unit and dispatching measures.
出处
《冶金动力》
2011年第4期15-17,共3页
Metallurgical Power
关键词
孤网运行
控制措施
isolated power grid operation