摘要
文章介绍了江口水电厂左岸溢洪道及进水闸基础地质勘察的工程实例,采取综合勘探测试等手段,复核并查明左岸溢洪道及进水闸的工程地质、水文地质条件,建基面混凝土与岩体接触和胶结情况,为基础防渗处理及加固设计方案优化、施工提供了依据。
This paper introduced foundation geological exploration on the left-spillway and intake work in Jiangkou Hydropower Plant.By taking integrated exploration test method, the engineering geology,hydmgeology conditions, contacting and cementing conditions of foundation surface with the rock were checked. It provided the optimization scheme and construction for prevention and reinforcement design.
出处
《江西电力》
2011年第3期28-32,共5页
Jiangxi Electric Power