迁钢1580mm热轧旋流沉淀池设计

Design of Hydrocyclone Sedimentation Tank for Qian'an 1 580 mm Hot Strip Mill
原文传递
导出
摘要 通过工程实例,介绍热轧旋流沉淀池圆柱形壳体的设计计算方法及施工次序,提出设计理念及构造措施。本工程采用倒逆法施工,先施工支护墙,使得旋流沉淀池施工简单迅速,缩短了工期,为后续工程做了很好的铺垫。此种设计受力清晰明确,简单明了。侧重介绍旋流沉淀池的受力分析及外支护结构的合理利用以及主要弯矩的受力部位位置,并在该位置采取增设暗梁等构造措施。 Through engineering examples, this paper introduces the design and calculation method and construction sequence of cylindrical shell of hot- rolled hydrocyclone sediment tank , puts forward the design principles and structural measures. This project adopts inverse construction method. Construction of supporting parapet wall is done firstly to simplify and shorten construction of hydrocyclone sediment tank, to reduce the construction time, to well set off the coming engineering. The author believes that force is simple and clear in this design. The paper focuses on introduction of force analysis, rational utilization of external parapet wall construction, stressed position of main flexural torque on which buried beam and other construction measures are taken.
作者 周长华
出处 《工程与技术》 2011年第1期59-63,共5页
关键词 旋流沉淀池 圆柱形壳体 有限元分析 结构设计 构造措施 hydroeyelone cylindrical shell finite element analysis structural design structural measures
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部