北京地铁10号线呼家楼站的主体结构邻近桥桩且多处下穿管线,通过施工安全、工期、技术等方面的比较,并用数值计算分析不同施工方法对周围环境的影响,最终选定"站厅层、站台层顺作,整体逆作"的"PBA"法作为临近桥桩暗挖车站的施工方案。
The main structure of Hujialou station of Beijing Metro Line 10 is adjacent to bridge piles with pipelines traversing.According to the comparison of construction safety,construction period and technology,as well as the influence of different construction methods to surrounding environment by utilizing numerical calculating analysis,'Pile-Beam-Arc'(PBA) is eventually chosen as construction plan for tunnel excavation of metro station adjacent to bridge piles.