摘要
碾压混凝土坝与常规混凝土浇筑方式不同,内部监测仪器的埋设方法也应适当调整。总结多年仪器埋设的施工经验,提出了一些适合碾压混凝土坝施工的具体施工方法,可以有效提高内部监测仪器的完好率。
As different pouring methods between roller compacted concrete and normal concrete, the embedment of inner monitoring instruments varies. The paper summarized the instrument embedment experience and advanced some detailed construction method for roller compacted concrete dam, which guaranteed the instrument availability
出处
《大坝与安全》
2011年第3期25-28,共4页
Dam & Safety
关键词
碾压混凝土
监测仪器
埋设
roller compacted concrete
monitoring instrument
embedment