摘要 针对在2009年冰冻灾害袭击中施黎甲线3基杆塔的受损情况,根据现场覆冰情况建立合理的不均匀覆冰模型;通过有限元软件对受损杆塔进行力学分析,寻找受损原因;根据计算结果,得出导地线纵向张力和过载覆冰对杆塔强度的影响范围;并提出了在工程中预防线路不平衡张力和过载冰的一些建议和方法。 Based on the damage of transmission towers of Shibing-Liping transmission Line in ice storms occurred in 2009, according to the actual icing conditions, the article establishs a reasonable model of the uneven ice; with the finite element software, the article does the mechanical analysis about the damaged towers, looking for the reasons of damage; according to the results, the article find out the sphere of influence about strength of tower under the effect of unbalanced tension and overload ice coating of transmission line; the article proposes some suggestions and methods about the prevention of unbalanced tension and overload ice coating in engineering.
作者 时云洪 彭赤
出处 《南方电网技术》 2011年第A01期123-126,共4页 Southern Power System Technology
关键词 输电线路 紧凑型铁塔 不平衡张力 过载覆冰 power transmission line compact tower tmbalanced tension overload ice coating

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部