红沿河一期全范围模拟机的设计和开发 被引量:3

Design and Development of FSS Used at Hongyanhe NPP Phase
下载PDF
导出
摘要 模拟机作为核电站操纵员进行培训的必备工具是电站生产准备期间的关键路径。红沿河核电站模拟机作为国内首个采用自主化DCS(数字控制系统)建设的设备,其设计有着自身的特点,其开发经验对于后续同类电站的模拟机建设有着一定的参考意义。就模拟机供货商的设计和开发流程进行了阐述,并就模拟机测试取得的经验进行了介绍。为从事模拟机制造、测试和管理工作的人员提供参考。 Simulator is an essential tool in nuclear power plant for operator training and it is also critical node in preparing for the plant running. Hongyanhe Nuclear Power Plant (NPP) Simulator has its own characteristics of its design. The development experience for the subsequent construction of similar power plant simulator has certain reference significance. The design and development process of simulator are described,and the test experience was introduced.It provides reference for the manufacturing,testing and management staff.
出处 《系统仿真技术》 2011年第3期237-241,共5页 System Simulation Technology
关键词 模拟机 开发 设计 simulator development design
  • 相关文献

参考文献2

  • 1国家核安全局.HAF103核动力厂运行安全规定[R].北京:国家核安全局,2004.
  • 2American Nuclear Society. ANSI/ANS-3.5 nuclear power plant simulator for use in operator training and examination [ S ]. [ s. l. ]: American Nuclear Society, 1998.

同被引文献10

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...