资源约束多模式项目调度的遗传算法研究 被引量:2

Study on Multi-Mode Resource-Constrained Project Scheduling Problem Based on Genetic Algorithm
下载PDF
导出
摘要 针对以工期最短为优化目标的多模式资源约束优化调度问题进行研究,在建立数学模型基础上,采用改进遗传算法对模型进行求解.算法设计上,对各活动的执行模式进行统一编号,使模式的内部编号包含了时序约束、资源约束、工期等信息,针对活动执行模式采用特殊的整数编码方式,染色体基因由活动执行模式序号组成.对染色体结构设计了单点交叉和单点变异操作算子,采用锦标赛选择方法.通过实例验证了改进遗传算法在求解MMRCPSP上的有效性. To improve the Multi-Mode Resource-Constrained Project Scheduling Problem(MMRCPSP),based on constructed the mathematical model of MMRCPSP,a new genetic algorithm is proposed.The objective is to determine a mode and a start time for each activity such that all constraints are observed and the project duration is minimized.A special integer coding scheme is used in the algorithm,each gene represents the execution mode and the start time of an activity.By designing appropriate genetic operators,the proposed genetic algorithm is effective to solve this problem.The experimental result indicated the effectiveness of the algorithm.
作者 黄少荣
出处 《微电子学与计算机》 CSCD 北大核心 2011年第9期165-168,共4页 Microelectronics & Computer
基金 广东省自然科学基金项目(101754539192000000)
关键词 资源约束 多模式 项目调度 遗传算法 resource-constrained multi-mode project scheduling genetic algorithm
  • 相关文献

参考文献4

二级参考文献10

  • 1[4]Valadares Tavares."A review of the contribution of operational research to project management" European Journal of Operational Research,1,January,2002,P1~18.
  • 2Sprecher A,Hartmann S,Drexl A.An Exact Algorithm for Project Scheduling with Multiple Modes[J].OR Spektrum,1997,19(3):195-203.
  • 3Hartmann S,Drexl A.Project Scheduling with Multiple Modes:A Comparison of Exact Algorithms[J].Networks,1998,32(4):283-297.
  • 4Boctor F F.Heuristics for Scheduling Projects with Resource Restrictions and Several Resource-Duration Modes[J].International Journal of Production Research,1993,31(11):2547-2558.
  • 5Boctor F F.A New and Efficient Heuristic for Scheduling Projects with Resource Restrictions and Multiple Execution Modes[J].European Journal of Operational Research,1996,90(3):349-361.
  • 6Alcaraz J,Maroto C,Ruiz R.Solving the Multi-Mode Resource-Constrained Project Scheduling Problem with Genetic Algorithms[J].Journal of the Operational Research Society,2003,54(6):614-626.
  • 7Bouleimen K,Lecocq H.A New Efficient Simulated Annealing Algorithm for the Resource-Constrained Project Scheduling Problem and Its Multiple Mode Version[J].European Journal of Operational Research,2003,149(2):268-281.
  • 8刘士新,王梦光,聂义勇.多执行模式资源受限工程调度问题的优化算法[J].系统工程学报,2001,16(1):55-60. 被引量:24
  • 9刘士新,王梦光,唐加福.一种求解资源受限工程调度问题的遗传算法[J].系统工程学报,2002,17(1):1-7. 被引量:30
  • 10侯健,曲昌学,陈月明,王玉斗,周波.用基于实数编码的自适应遗传算法求解产量预测模型[J].石油大学学报(自然科学版),2002,26(3):55-58. 被引量:11

共引文献20

同被引文献19

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部