摘要
在分析预测广西煤炭需求及各铁路煤炭运量基础上,针对区域既有煤炭运输通道运煤能力与预测煤炭运量之间不足的情况,提出了需重点建设的煤炭铁路运输通道项目:近期南昆线增建二线、黔桂线麻尾~金城江段新建双线、金城江~柳州段增建二线、焦柳线电气化改造、湘桂线电气化改造,远期焦柳线增建二线;最后对各主要煤炭运输通道能力适应性进行分析后认为,重点煤炭铁路运输通项目实施后,区域能源安全和经济结构调整将得到充分保障。
Based on the analysis and prediction of the coal demand and railway transportation volume of coal,to solve the differences between the existing coal transportation capacity and the expected transportation volume,railway project of coal transportation is proposed:construction of second line Nankun railway second line,second line for Guiqian railway,Mawei-Jincheng section,Jinchengjiang-Lvzhou section.At last,after an analysis of the adaptability of railway transportation,it proves that the regional energy safty and the adjustment of economic structure can be ensured by the construction of key coal transportation railway.
出处
《铁道建筑技术》
2011年第8期47-51,共5页
Railway Construction Technology
关键词
铁路运输
通道能力
适应性分析
对策研究
railway transportation
channel capacity
adaptability analysis
adaptability study