摘要
新安煤矿+535水平是设计生产水平,由于地质条件复杂,构造应力大,大部分巷道工程均出现了严重变形破坏的现象,严重影响矿井的安全生产。文章基于巷道失稳变形破坏特点及原因分析,提出了控制深部巷道围岩变形破坏的关键技术,进行了合理支护技术参数的确定,并对锚索(双托板)与钢筋混凝土联合支护的+535主石门二号交岔点试验段进行了十二个月的观测,发现巷道围岩的变形很小,且已连续三个月变形速度趋于零,从而直接验证了该支护技术方案的正确性。
The + 535 Level of Xin 'an Mine was the designed production level. Due to the complicated geological conditions and high structure stress, a major part of the mine roadway project had a serious deformation failure phenomenon appeared. Thus the mine safety production was seriously affected. Base on the stability lost and deformation failure features of the mine roadway and the cause analysis, the key technology to control the surrounding rock deformation failure of the deep mine roadway was provided. The parameters of the rational support technology were determined. A 12 month observation and measurement was conducted in the trial section at the No. 2 cross point roadway of + 535 main crosscut with the anchor (double plates ) and reinforced concrete combined support system. The trial results showed that the deformation of the mine roadway was small and the deformation speed in a continued three month was close to zero. Thus the correctness of the support technical plan could be directly verified.
出处
《煤炭工程》
北大核心
2011年第9期34-36,共3页
Coal Engineering
关键词
深部巷道
锚索
钢筋混凝土
联合支护
deep mine roadway
anchor
reinforced concrete
combined support