考虑资源传递时间的多项目调度问题 被引量:9

Multi-project scheduling problem with resource transfer time
下载PDF
导出
摘要 现有多项目调度研究一般假定执行项目所用的资源在各项目之间传递时不需要花费时间和成本,这与许多实际情况不吻合。为缩小理论研究与实际情况的差距,提出一种考虑资源传递时间并以多项目总工期及各个项目工期的加权和最短为目标的多项目调度模型,该模型同时考虑了资源传递时间约束以及资源传递数量约束。提出一种基于三级启发式规则解码的改进遗传算法,通过实例计算并将结果与其他算法进行比较,验证了算法的有效性。 Most multi-project scheduling reseraches proposed in the literature so far are based on an assumption that resources are transferred from one project to the other without any expense of time or cost,but this assumption doesn't in accordance with the practical situation.To reduce the gap between theoretical studies and reality,a multi-project scheduling model with considering transfer time was proposed.The model was targeted at the weighted and shortest duration of the multi-project and each project,meanwhile,both transfer time constraint and transfer number constraint of resource were simultaneously considered.An improved genetic algorithm based on three-stage heuristic rules decoding was proposed.Through the practical examples and comparison to other algorithms,the effectiveness of the algorithm was verified.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2011年第9期1921-1928,共8页 Computer Integrated Manufacturing Systems
基金 国家863计划资助项目(2007AA04Z190 2009AA043301) 国家自然科学基金资助项目(50705036)~~
关键词 项目调度 传递时间 资源约束 遗传算法 project scheduling transfer time resources constraint genetic algorithms
  • 相关文献

参考文献11

  • 1SONDA E, PHILIPPE F. A hybrid rank based evolutionary algorithm applied to multi-mode resource constrained project scheduling problem[J]. European Journal of Operational Research, 2010,205(1) :31-41.
  • 2LOVA A, TORMOS P, Analysis of scheduling schemes and heuristic rules performance in resource constrained multi project scheduling[J]. Annals of Operations Research, 2001,102 ( 1/2/3/4):263-286.
  • 3应瑛,寿涌毅,李敏.资源受限多项目调度的混合遗传算法[J].浙江大学学报(工学版),2009,43(1):23-27. 被引量:22
  • 4KIM K W,YUN Y S, YOON J M, et al. Hybrid genetic algorithm with adaptive abilities for resource-constrained multiple project scheduling[J]. Computers in Industry, 2005,86(2):143-160.
  • 5GONCALVES J F, MENDES J M, RESENDE M G. A genetic algorithm for the resource constrained multi-project scheduling problem[J]. European Journal of Operational Research, 2008,189(3) : 1171-1190.
  • 6DOREEN K, ARMIN S. Managing and modeling general resource transfers in (multi-) project scheduling [J]. OR Spectrum,DOI:10. 1007/s00291-008-0144-5.
  • 7PAUL H, JAMES R. Internationalization, product development and performance outcomes: a comparative study of 10 countries[J]. Research in International Business and Finance, 2009,23(2) :169-180.
  • 8FRANCISCO B, ROSA B. Theoretical and practical fundamentals for multi-ohjective optimization in resource-constralned project scheduling problems[J]. Computer & Operations Research,2011,38(1):51-62.
  • 9DOREEN K, ARMIN S. A heuristic solution framework for the resource constrained multi-project scheduling problem with sequence-dependent transfer times[J]. European Journal of Operational Research, 2009,197(2) :492-508.
  • 10BROWNING T R, YASSINE A A. Resource-constrained multi-project scheduling: Priority rule performance revisited [J]. International Journal of Production Economics, 2010, 126(2) :212-228.

二级参考文献10

  • 1寿涌毅.资源约束下多项目调度的迭代算法[J].浙江大学学报(工学版),2004,38(8):1095-1099. 被引量:46
  • 2LOVA A, TORMOS P. Combining random sampling and backward-forward heuristics for resource-constrained multi-project scheduling [C]//Proceedings of the 8th International Workshop on Project Management and Scheduling. Valencia, Spain:[s. n. ], 2002 : 244 - 248.
  • 3KUMANAN S, JEGAN J G, RAJA K. Multi-project scheduling using an heuristic and a genetic algorithm [J]. The International Journal of Advanced Manufacturing Technology, 2006, 31(3-4): 360-366.
  • 4GONCALVES J F, MENDES J J M, RESENDE M G C. A genetic algorithm for the resource constrained multi-project scheduling problem[J]. European Journal of Operational Research, 2008, 189(3) : 1171 - 1190.
  • 5SPRECHER A, KOLISCH R, DREXL A. Semi-active, active, and non-delay schedules for the resourceconstrained project scheduling problem [J].European Journal of Operational Research, 1995, 80(1) : 94 - 102.
  • 6KURTULUS I, DAVIS E W. Multi-project scheduling: categorization of heuristic rules performance[J].Management Science, 1982, 28(2):161 - 172.
  • 7HARTMANN S. A competitive genetic algorithm for resource-constrained project scheduling[J]. Naval Research Logistics, 1998, 45(7) : 733 - 750.
  • 8LI K Y, WILLIS R J. An iterative scheduling technique for resource-constrained project scheduling[J]. European Journal of Operational Research, 1992, 56(3): 370-379.
  • 9TSAI D M, CHIU H N. Two heuristics for scheduling multiple projects with resource constraints[J]. Construction Management and Economies, 1996, 14(4):325- 340.
  • 10KURTULUS I, NARULA S C. Multi-project scheduling: analysis of project performance [J].IIE Transactions, 1985, 17(1): 58-66.

共引文献21

同被引文献66

引证文献9

二级引证文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部