摘要
在上海港罗泾港区二期矿石码头工程的施工中,针对矿石堆场皮带机及堆取料机基础建设情况,采用了"浅层处理,利用使用期矿石分级压载,地基处理分几步到位,使用期调整"等新的建设理念。提出了相应的施工参数,进行了工程的实际应用,取得了成功。详细介绍了做法和效果,可供参考。
Pointing against the situation of foundation construction for the ore yard belt conveyer and stacker-reclaimer, the new ideal and technology has been adopted in the construction of the ore yard of Luojing Ore Terminal (Phase 2), which are"treating of shallow layer, pressing with the ore arriving then by stage, foundation treating by stage and adjustment in the usage period."Relative constructive parameters has been put forward and applied which is successful. It introduces the methods and results, which could be referenced.
出处
《港口科技》
2011年第9期24-26,34,共4页
Port Science & Technology
关键词
港口
建设
堆场
地基处理
使用期调整
理念
port construct yard ground treatment adjustment in the usage period ideal