哈达山节制闸闸室底板冻胀数值模拟

Numerical Simulation for Frost Upheaval of Bottom Plate of Controlling Gate Chamber at Hada Mountain
下载PDF
导出
摘要 哈达山水利枢纽输水干渠工程是吉林省特大灌区工程,肩负增长百亿斤商品粮的重任。施工单位在春天做施工准备时发现闸室底板中间位置出现贯穿性裂缝,伴随着底板抬高现象。对闸室底板进行有限元建模,计算底板的温度场和应力场在浇筑完成后随环境温度的变化情况。结果表明,由于寒区冬季环境温度低,施工阶段闸底板压重不足情况下越冬,在结构上会极大加剧闸门槽这一薄弱部位开裂的可能性。 Water Trunk Canal of Hada Mountain Hydro Project is the biggest irrigation construction of Jilin Province. It bears a most important task of making sure of increasing by billions kilograms of grains. The constrcuction company found perforliate cracks appearing in the middle of the bottom plate of gate chamber, with the bottom plate heaving, when they prepared for constuction in spring. This text herewith mainly states the model formation of finite element, for bottom plate of gate chamber. , and calcullates the changes of tempretuer field and the stress field of the bottom plate, after pouring, which is with the change of its enviromental tempreture. The results suggest that during the constructing, the prosibilities of cracking appearing at the weak part of the gate slot will be extreamly increased , if the eonstrucion is constructed at a lowest envoironment tempreture , in winter of the cold area, but the bottom plate being without enough pressure.
作者 闫金良
出处 《水利科技与经济》 2011年第9期40-42,共3页 Water Conservancy Science and Technology and Economy
关键词 寒区冬季 闸底板 冻胀 裂缝 数值模拟 winter in cold area bottom plate of gate chamber frost upheaval cracking numerical simulation
  • 相关文献

参考文献4

  • 1H.A.崔托维奇(苏).冻土力学[M].张长庆,朱元林译.北京:科学出版社,1985.
  • 2Ma Wei ( Lanzhou Gansu). Review and Prospect of the Studies of Ground Freezing Technology in China [ S ]. Journal of Glaciology and Geocryology, 2001,23 ( 3 ) : 218 -224.
  • 3李萍,徐学祖,陈峰峰.冻结缘和冻胀模型的研究现状与进展[J].冰川冻土,2000,22(1):90-95. 被引量:71
  • 4王助成,邵敏.有限单元法基本原理和数值方法[M].北京:清华大学出版社.1996.

二级参考文献5

共引文献71

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部