摘要
宁波市"五路四桥"工程全长32 km,共计5条快速路和主干路,包括4座跨江特大桥和6座大型互通式立交。该文结合宁波市"五路四桥"工程,从招投标管理、工程合同、投资、质量、安全、进度等方面总结了建设管理经验,可供类似项目参考。
The total length of Ningbo City 'Five-Road and Four-Bridge' Project is 32 km.There are five expressways and main trunk roads including four crossing-river super-large bridges and six large interchanges.According to Ningbo City 'Five-Road and Four-Bridge' Project,the article sums up the construction management experience in the respects of bidding and tendering management,engineering contract,investment,quality,safety and schedule able to be referred for the similar projects.
出处
《城市道桥与防洪》
2011年第9期204-206,329,共3页
Urban Roads Bridges & Flood Control
关键词
“五路四桥”
工程建设
项目管理
宁波市
'Five-Road and Four-Bridge',engineering construction,project management,Ningbo City