矿业工程项目施工工期可靠性预测研究 被引量:5

Construction time reliability forecasting of mining project
下载PDF
导出
摘要 工期是矿业工程项目管理的三大目标之一,本文引入施工工期可靠性这一指标衡量矿业工程项目工期管理水平。基于蒙特卡洛模拟法与计划评审技术相结合提出了工程项目施工工期可靠性的预测模型。与传统计划评审技术方法相比,用蒙特卡洛模拟法求解的优点在于通过模拟构造多个方案,弥补了传统计划评审技术的假设条件造成的误差,提高了计算精度,更加符合实际工程的情况;最后以一工程实例进行了应用。 Time is one of the three objectives for mining project,and construction time reliability as a appraisal index for time is introduced to measure time management level of mining project.Based on the method combined of Monte Carlo simulation and PERT,the forecasting model of construction time reliability is built.Compared with traditional PERT,the advantage of Monte Carlo simulation is to compensate the error caused by assumptions of PERT and to improve calculation accuracy.Finally,a case is chosen as the application of such theory and method.
出处 《西安科技大学学报》 CAS 北大核心 2011年第5期593-597,共5页 Journal of Xi’an University of Science and Technology
基金 陕西省教育厅人文社科专项科研资助项目(11JK0170)
关键词 矿业工程项目 施工工期可靠性 蒙特卡洛模拟 计划评审技术 mining project construction time reliability Monte Carlo simulation PERT
  • 相关文献

参考文献7

二级参考文献30

共引文献64

同被引文献31

引证文献5

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部