摘要
积石峡水电站工程已经进入尾期,施工测量控制网网形需要进行整体优化、补建。文章主要从网形结构优化、控制点点位优化与补建、平面控制点观测与计算等几方面对控制网的改造进行阐述。
construction of Jishixia Hydropower Project is coming to the end, outline of the, construction survey control network needs to be optimized and constructed additionally. In this paper, the control network updating is discussed in terms of optimization of the network structure, optimization and additional establishment of, control point position, observation and computation of plane control points.
出处
《西北水电》
2011年第B09期108-110,共3页
Northwest Hydropower
关键词
施工测量
控制网
监测
Construction survey
control network
monitoring