面向振动控制协同设计任务的时间模型研究

Research on the Time Model of Collaborative Design Task on Vibration Control
下载PDF
导出
摘要 在基于压缩机管线振动控制项目的协同系统中,各子任务分配和调度是十分关键的。合理的任务分配和调度可以优化振动控制项目实施进程,提高项目的执行效率。笔者考虑管线振动控制项目中任务之间的相互约束关系,以项目总的持续时间为目标,任务调度为设计变量,建立项目协同任务调度的数学模型,并应用遗传算法对其进行求解,得出任务的最优调度策略和任务调度的甘特图,并进行验算分析。分析结果显示在最优调度策略下,项目执行效率明显提高,总的执行时间大大缩短,这种基于遗传算法的时间模型可为项目任务的合理分配提供一种很好的参考。 The scheduling of collaborative design task is the key to the cooperative system of compressor pipeline vibration project. The logical scheduling of collaborative design task can optimize the process of compressor pipeline vibration project and improve the project efficiency accordingly. Considering the mutual constraining relationship between the tasks of compressor pipeline vibration project, the present author establish a mathematical model of collaborative design task scheduling. Such a model takes the task scheduling as the design variable, aiming at minimizing the overall time of the project, A genetic algorithm was employed to resolve the mathematical model, achieve the superior scheduling strategy and a Gantt chart of the task sched- uling, and verify the result of calculation. The results show that the implementation efficiency of the project is greatly improved, and the overall operating time is shortened by employing the superior scheduling strategy. Therefore, the time model, which is based on the genetic algorithm, can be a good reference for the scheduling of collaborative design task.
出处 《北京石油化工学院学报》 2011年第3期16-20,共5页 Journal of Beijing Institute of Petrochemical Technology
关键词 协同设计 时间模型 遗传算法 管线振动控制 collaborative design task time model genetic algorithm pipeline vibration control
  • 相关文献

参考文献4

二级参考文献33

  • 1王志亮,张友良.耦合任务的重叠执行问题研究[J].计算机集成制造系统,2006,12(6):947-954. 被引量:12
  • 2钟一文,杨建刚.异构环境下独立任务分配问题的免疫遗传算法[J].小型微型计算机系统,2006,27(8):1498-1502. 被引量:3
  • 3陈平,杨文玉.复杂产品结构的模块化聚类及设计迭代量计算[J].中国机械工程,2007,18(11):1346-1349. 被引量:6
  • 4ULRICH K T,EPPINGER S D. Product design and development[M]. New York,N. Y. ,USA:McGraw-Hill, 2000.
  • 5XIAO Renbin,SI Shangwen. Research on the process model of product development with uncertainty based on activity overlapping[J].Integrated Manufacluring Systems, 2003, 14(7): 567-574.
  • 6SIGAL C E, PRITSKER A B. Management decision making:a network simulation approach[M]. Upper Saddle River, N. J. ,USA:Prentice Hall, 1983.
  • 7EPPINGER S D, NUKALA M V,WHITNEY D E. Generalized models of design iteration using signal flow graphs[J]. Research in Engineering Design, 1997, 9(2):112 -123.
  • 8SMITH R P, EPPINGER S D. A predictive model of sequen tial iteration in engineering design[J]. Management Science, 1997, 43(8):1104- 1120.
  • 9SMITH R P, EPPINGER S D. Identifying controlling features of engineering design iteration[J].Management Science, 1997, 43(3) :276-293.
  • 10YASSINE A A, JOGLEKAR N, BRAHA D,et al. Information hiding in product development: the design churn effect [J]. Research in Engineering Design, 2003, 14(3) :145-161.

共引文献59

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部