摘要
西江引水工程建成后,西江水源将全面置换广州市西北部石门、江村和西村水厂的原有水源。优质的西江水入穗后,广州市中心城区的供水水质将得到全面提升。为确保西江水源置换管网水质安全,通过管网水质保障关键技术研究、优化出厂水关键水质指标、建立立体化监测网络、强化管网保障措施和完善管网水质应急预案等,构建了西江水源置换管网水质保障体系,确保了目前国内最大规模的水源置换(置换水量为242×10~4m^3/d)在复杂的供水管网中成功完成。
Xijiang River water source replaced the original water sources of Shimen, Jiangcun and Xicun waterworks in northwest of Guangzhou, after Xijiang River diversion project was finished. Water quality in Guangzhou is significantly improved. In order to safeguard water quality, the guarantee system of distribution system water quality was established by key technical research of distribution system water quality safety, optimization of major finished water quality indices, establishment of 3D water monitoring network, reinforcement of pipe guarantee measures, and perfection of distribution system water quality emergency response plan. The maximum water source replacement ( replacement water quantity of242×10^4m3/d) was carried out successfully in the complex distribution system in China.
出处
《中国给水排水》
CAS
CSCD
北大核心
2011年第20期1-4,共4页
China Water & Wastewater
基金
国家水体污染控制与治理科技重大专项(2009ZX07423-004)
关键词
西江水源
水源置换
管网水质
保障体系
Xijiang River water source
water source replacement
distribution system water quality
guarantee system