摘要
结合临午公路改建工程较详细的对热熔标线的施工工艺进行了论述,并提出质量控制方法,针对工程中出现的质量缺陷进行了原因分析,采取了相应的质量控制措施,以确保标线质量满足标准要求,进而保证道路交通安全。
Combining with the reconstruction project of Lin-Wu highway, this paper detailedly discussed the construction technology of hot melt marking, and put forward the quality control methods, made cause analysis on existing quality defects in the engineering, took corresponding quality control measures, to ensure the marking quality meet the standard requirements, thus ensured the road traffic safety.
出处
《山西建筑》
2011年第31期138-139,共2页
Shanxi Architecture
关键词
热熔标线
施工工艺
质量控制措施
hot melt marking, construction technology, quality control measure