矮墩连续刚构桥顶推合龙的计算分析与施工实践 被引量:2

Calculation and Construction of Closure of Low-Pier Continuous Rigid Frame Bridge with Pushing Force
下载PDF
导出
摘要 合龙时实施顶推是优化矮墩及高温合龙连续刚构桥长期受力状态的重要途径。结合工程实践,探讨了对边主墩施加水平顶推力和墩顶侧向位移的计算过程,并详细介绍了顶推施工的控制指标。现场实测数据证明,预定的顶推力和墩顶位移设置合理,实测顶推力及墩顶侧向位移均在预期控制范围内。 Loading pushing force before closure construction is an effective measures which optimize long-term effect of low-pier continuous rigid frame bridge closed on high-temperature.Combined with engineering practice,it has been discussed that the calculation process of pushing force on the top of the hypo-middle piers and horizontal displacement,and the control indicators of pushing implementing were introduced.Practical results showed that assumptive pushing force and horizontal displacement were appropriate and controllable,and accorded with actual pushing force and lateral displacement.
出处 《交通标准化》 2011年第20期101-104,共4页 Communications Standardization
关键词 连续刚构桥 顶推合龙 顶推力 侧向位移 continuous rigid frame bridge closure with pushing pushing force horizontal displacement
  • 相关文献

参考文献5

二级参考文献12

共引文献50

同被引文献25

引证文献2

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部