摘要
以西藏旁多水电站大坝防渗墙施工为依托,研究了超深防渗墙施工中槽段连接的难点和关键点,合理确定了接头管的起拔时间、起拔力等参数。在混凝土"稳固"特性基础上,采取数值模拟技术研究了接头管的最佳拔管时机,确定了不同条件下的拔管力,以便为工程设计与施工提供相关技术依据。
Based on the construction of the cut-off wall in the dam of Pangduo Hydropower Station in Tibet, the difficulties and key points from the construction of the joint section of the super-deep cut-off wall are studied herein; in which the parameters such as the pulling time, pulling force for pulling out of the joint-pipe, etc. are reasonably determined. In accordance with the stabilized characteristics of concrete, the optimum time for pulling-out of the joint-pipe is studied based on a numerical simulation, and then the relevant pulling forces under various conditions are determined as well, so as to provide the related technical basis for both the design and construction of the project concerned.
出处
《水利水电技术》
CSCD
北大核心
2011年第10期87-90,共4页
Water Resources and Hydropower Engineering
基金
国家自然科学基金创新研究群体科学基金(51021004)
教育部"长江学者和创新团队发展计划"创新团队(IRT0851)
国家自然科学基金(50809046)
关键词
超深防渗墙
接头管
拔管工艺
拔管力
西藏旁多水电站
super-deep cut-off wall
joint-pipe
pipe pulling-out technology
pulling force
Pangduo Hydropower Station in Tibet