考虑进度不确定的土石坝填筑施工成本风险分析 被引量:2

Cost-risk analysis of earth dam construction with considerations of schedule uncertainty
原文传递
导出
摘要 在气象等不确定因素的影响下,土石坝填筑施工进度具有较大的风险,并伴随着施工成本风险的发生。在定义施工成本风险的基础上,构建了进度不确定条件下施工成本风险分析模型;探讨了施工成本不确定性及其分布,以及施工赶工成本分析计算方法;针对施工成本风险分析模型的特点,采用离散化方法,得到了施工成本风险计算公式。算例结果表明,在进度不确定条件下,施工成本存在较大的风险性,这在工程投标报价、施工管理决策中是不能忽略的。 Earth dam construction,if influenced by uncertain factors such as meteorological condition,is often subjected to a great risk in construction progress and a risk in construction cost.In such cases,an appropriate cost-risk analysis model is needed to take various uncertain factors into account.In this study,construction cost risk was defined and a cost-risk analysis model with considerations of schedule uncertainty was developed.With a discussion on the uncertainty and distribution of construction cost,a calculation method of crash cost was also presented.A cost-risk formula was derived by the same discretization method as that in the cost-risk model.Case studies show that the uncertain construction delay that causes great risk to construction cost,should not be neglected in bidding or construction management decision-making.
出处 《水力发电学报》 EI CSCD 北大核心 2011年第5期229-233,247,共6页 Journal of Hydroelectric Engineering
关键词 水电工程管理 施工成本 风险分析 土石坝 工程进度 water-power engineering management construction costs risk analysis earth dam construction scheduling
  • 相关文献

参考文献10

  • 1Isidore J Leroy, Edward Back W. Multiple simulation analysis for probabilistic cost and schedule integration [ J]. Journal of Construction Engineering and Management, 2002, 128 (3) : 211 - 219.
  • 2徐哲,吴瑾瑾,汪阳青.基于Monte Carlo多重仿真的费用与进度联合置信估计[J].系统仿真学报,2006,18(12):3334-3337. 被引量:12
  • 3倪蔚颖.蒙特卡洛模拟在项目成本风险分析中的应用[J].大众科技,2008,10(7):216-218. 被引量:7
  • 4陈晓宇.工程项目风险性成本管理[J].建筑施工,2008,30(5):417-419. 被引量:6
  • 5郭宇,刘尔烈.应用蒙特卡罗方法改进项目成本风险分析[J].天津大学学报(自然科学与工程技术版),2002,35(2):199-202. 被引量:19
  • 6Elazouni A M. and Abido M A. Finance-based scheduling of multiple construction projects using multiobjective evolutionary algorithms [ C]. Proceedings, Annual Conference-Canadian Society for Civil Engineering, 2009.
  • 7Zheng D X M and Thomas Ng, S. Stochastic time-cost optimization model incorporating fuzzy sets theory and nonreplaceable front [ J]. Journal of Construction Engineering and Management, 2005,131 (2) :176 -86.
  • 8Chassiakos and Sakellaropoulos time-cost optimization of construction projects with generalized activity constraints [ J]. Journal of Construction Engineering and Management, 2005,131 ( 10 ) : 1115 - 1124.
  • 9Malcolm D G. , Roseboom J H. Application of a technique for research and development evaluation [J]. J. opns. Res. , 1959, (7): 646-669.
  • 10Littlefield P H. and Randolph. Reply:An answer to sasieni' s question on PERT times [ J]. Mgmt. Sci. , 1987, 33 (10) :1357 - 1359.

二级参考文献8

共引文献38

同被引文献18

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部