摘要
针对输电线路铁塔基础施工中,大量基础存在地质条件差、承台基础施工方量大、施工周期长等特点,详细介绍了输电线路大跨越大承台基础施工的难点、特点,在混凝土内部设置冷却循环水管及温度检测、表面养护等技术方面采取了有效的措施,并取得了满意的效果。
In the construction of the iron tower foundation power transmission lines,the paper indicates some features,including the weak geological conditions in the foundation,the tough tasks for the pier construction,and the long construction period,the paper introduces the difficulties and features of the crossing pier foundation construction of the power transmission lines,and adopts the effective measures in the cooling cycle water pipe,the temperature checking,and the surface maintenance of the concrete internal apparatus,and achieves satisfactory effects.
出处
《山西建筑》
2011年第32期102-103,共2页
Shanxi Architecture
关键词
输电线路
大体积铁塔基础
施工技术
power transmission line
large iron tower foundation
construction technique