摘要 目前众多建筑工程中的管桩连接均采用人工焊接,焊接质量不良引起的焊接问题占用了相当比例,尤其是抗拔桩质量更难保证,本文介绍了预应力混凝土管桩机械快速螺纹连接的构造、特点、施工安装方法及其在工程中的应用情况,这种新的连接方法具有施工工期短,不受气候环境和人为因素的影响,综合经济效益显著等特点。 Presently the joining of the tubular pile of the numerous construction engineering mostly adopted the manual welding,in which the bad welding quality often caused a lot of sealing problems especially the welding quality of the uplift pile.And the construction quality,installation method and engineering application of the quick threaded connection of the prestressed concrete tubular pile machinery was introduced in this article,which this kind of the new connection method had the short construction period and free from the climatic environment and influence of the human factor,and had the remarkable economy of integration and so on.
作者 林基
出处 《福建建筑》 2011年第10期109-110,共2页 Fujian Architecture & Construction
关键词 管桩 螺纹连接 机械连接 快速 Tubular Pile The threaded connection Mechanical connection Rapidness.
  • 相关文献

参考文献5

  • 1DBJ13-58-2004,预应力混凝士管桩机械快速连接接头施工及验收规程[S].
  • 2DBJ13-57,先张法预应力高强混凝土管桩[S].
  • 3GB50010-2002.混凝土结构设计规范[S].[S].,..
  • 4GB50007-2002.建筑地基基础设计规范[S].[S].,..
  • 5JGJ94-94.建筑桩基技术规范[S].[S].,..

共引文献4890

同被引文献3

  • 1GB50017-2003.钢结构设计规范[S].[S].,..
  • 2DBJl3--2006,福建省地方标准《先张法预应力混凝土管桩基础技术规程》[S].
  • 310G409,国家建筑标准设计图集《预应力混凝土管桩》[S].

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部