摘要 结合铁建设[2005]160号铁路混凝土工程施工质量验收补充标准中相关要求,对高速铁路箱梁预制温控措施进行了介绍,分别阐述了原材料温控措施和浇筑期间温控措施,并提出了具有指导性的几点建议,以期保证箱梁施工质量。 Combining with the relative requirements of the supplementary standards for the Construction Quality Acceptance of Railway Concrete Projects [ 2005 ] No. 160 railway construction, the paper introduces the prefabricate temperature control measures of box girders of expressways, illustrates the temperature control measures of the raw materials and the temperature control measures in the grouting period, and points out some directive suggestions, so as to ensure the construction quality of the box girder.
作者 王玉珍
出处 《山西建筑》 2011年第33期165-166,共2页 Shanxi Architecture
关键词 高速铁路 箱梁 混凝土 温控措施 express railway, box girder, concrete, temperature control measures
  • 相关文献

参考文献4

  • 1铁建设[2005]160号,客运专线铁路桥涵工程施工质量验收暂行标准[S].
  • 2科技基[2005]101号,客运专线高性能混凝土暂行技术条件[S].
  • 3铁科技[2004]120号,客运专线预应力混凝土预制梁暂行技术条件[S].
  • 4吴松.预应力连续箱梁施工技术[J].山西建筑,2010,36(14):295-296. 被引量:12

二级参考文献1

  • 1交通部第一公路工程总公司.桥涵[M].北京:人民交通出版社.2005.

共引文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部