摘要
阐述柏叶口水库混凝土面板堆石坝挤压边墙的施工过程,产生偏差的原因、减少偏差的改进措施。
The paper introduces the process to construct extrusion side wall of concrete facing rockfill dam of Baiyekou Reservoir,analyzes the causes to form wall's deviation and presents the improvement measures to decrease deviation.
出处
《山西水利科技》
2011年第4期8-9,共2页
Shanxi Hydrotechnics
关键词
混凝土面板堆石坝
挤压边墙
偏差
原因
改进措施
concrete facing rockfill dam extrusion side wall deviation cause improvement measure