摘要 随着滩涂围垦工程建设的进一步深入,滩涂围垦工程中的一些问题逐渐显露出来,这其中争议比较多的问题便是沉降工程量的问题。本文客观分析了滩涂围垦工程中沉降工程量变化的原因,提出其应对措施。 With the further development of the tidal flat reclamation, some problems from such a project gradually appear, among which the problem with more disputes is the construction work quantity from the settlement. The changing causation of construction work quantity from settlement in the reclamation project is objectively analyzed herein, and then the relevant counter- measures are put forward as well.
出处 《水利水电技术》 CSCD 北大核心 2011年第11期92-94,共3页 Water Resources and Hydropower Engineering
关键词 滩涂围垦工程 沉降工程量 原因与对策 tidal flat reclamation project construction work quantity from settlement causation and countermeasures
  • 相关文献

参考文献3

  • 1海堤工程设计规范SL 435-2008[S].2008.
  • 2中介机构执、啦成果差错率参考标准(暂行)(2008)[S].浙江省造价站.
  • 3水利水电工程标准施工招标文件(2009)[S].北京:中国水利水电出版社,2009.