摘要
结合现场施工的实际情况,通过对试验及运用阶段的归纳总结,从工艺原理、施工工艺、施工要点及质量检测监控等方面,对“高真空排水+强夯+垫层+冲击碾压”新联合工法进行了系统的阐述。
Combining the practical project,engineers adopt some methods to treat airport foundation,such as high vacuum dewatering method,dynamic compaction method,bedding course method,and impactive rolling method.Based on the summary of experiment,the author presents these methods from three aspects,including process principle,construction feature,and quality control.
出处
《施工技术》
CAS
北大核心
2006年第S1期8-11,24,共5页
Construction Technology
关键词
地基处理
软土地基
强夯
冲击碾压
foundation treatment
soft foundation
dynamic compaction
impactive rolling