各种工法在水库除险、重要堤防工程中采用,由于成墙原理不同,在成墙体搭接时容易产生分叉等问题。经过近几年的实践,得出当采用不同的施工方法时,其接头应采用不同的工艺,这样才能保证防渗墙体间的搭接质量。
When the different construction methods are used in reservoir emergency and important embankment engineering,some problems such as displacement etc.in the overlap of wall are easily appeared because of the different wall shaping theory.The several years engineering practice show that different construction techniques are used with the different construction methods,which can assure the overlap quality of anti-leakage wall.
出处
《施工技术》
CAS
北大核心
2006年第S2期186-188,共3页
Construction Technology
关键词
防渗墙
接头
裂缝
处理
anti-leakage wall
adapter
crack
treatment