摘要
本文以巴东县滩坪滑坡锚索工程、黄土坡滑坡锚杆工程为例,介绍了锚固技术在三峡库区的应用现状及存在的一些问题。并对今后三峡库区岩土锚固技术应用的有关设计和施工的若干问题提出了自己的看法,以期和同行探讨,同时也希望本文能对今后岩土锚固技术在三峡库区得到更好的应用有所帮助。
This text come down with yellow slight slope stock project , beach level ground come down anchor ask for project, high slope prop up project of partial toing as the example, has introduced the firm application current situation in the reservoir area of Three Gorges of technology of the anchor, and to firm several key problems that use of soil anchor of rock of reservoir area of Three Gorges in the future, if design , corrode and protect of stock,, stock type and his scope of application , stock construct etc. and put forward the suggestion.
出处
《工程勘察》
CSCD
北大核心
2006年第S1期177-181,共5页
Geotechnical Investigation & Surveying
关键词
岩土锚固技术
三峡库区
现状
建议
Reservoir area of Three Gorges
Firm technology of soil anchor of rock
Current situation
Propose