尊村补充水源工程是为解决尊村泵站长期脱流问题提出的。根据河道变化的特点,尊村补充水源采取“提、引、挖、堵”综合措施来实现。其组成部分主要有:泵船、船池、输水管道、输水渠、输电线路、挖泥机械等。
Zuncun supplementary water project is proposed to solve the long-term problem of that the flow of the Yellow River separates from the intake of Zuncun pumping station.According to the characteristics of change of local river course,the comprehensive measures of “lifting water by pump-ship,diverting water by canal and natural branch river course,digging the diverting or conveyance canal when necessay by excavator,and blocking the branch river course downstream”is taken.The system consists of pump,ship,ship pool,water-conveyance pipeline,canal,power transmission line,dredging equipment and so on.
出处
《山西水利科技》
1999年第S1期71-72,共2页
Shanxi Hydrotechnics
关键词
泵船
黄河小北干流
尊村泵站
渠道
Pump and Ship Canal Pumping Station Yellow River