根据京南电站裂缝的不同情况采用水泥砂浆和化学灌浆等不同技术措施和施工方法进行处理,经检查试验,各项物理力学指标均达到设计要求,取得了优良的效果。
According to different status of concrete cracks of structures in Jingnan Hydropower station,different treatment methods and processes tvers adopted such as cement grouting, chemical grouting and etc..After tested and examined, all physical mechanical indexes meet design requirement.