摘要
对溢流坝挑流设计中挑坎的形状、反弧半径、挑坎顶高程、中墩尾墩位置等方面进行分析,并通过水工模型试验验证,说明乌宋岗水电站溢流坝挑流设计是合理的。
The shape of the flip bucket,the radius of the reverse circle,the top elevation of the flip bucket,the position of the intermediate piers of the overflow dam in Wusonggang Hydropower Plant were analysed.The design was proved to be reasonable throngh hydraulic model test.
出处
《黑龙江大学工程学报》
1998年第4期66-68,共3页
Journal of Engineering of Heilongjiang University
关键词
溢流坝
挑流设计
模型试验
overflow dam,ski jump design,model test.