根据小干沟电站特点,首次采用了月牙肋型钢岔管,使用微机技术,缩短了设计周期,加快了施工进度,取得了显著的社会和经济效益。
? The bifurcated penstock with internal crescent web reinforcement was applied in xiaogangou Hydropower station.with the application of CAD technology,the designig period was shortened,resulting in better social and economic benelit.