摘要
In this paper the water-taking characteristics of the first,the second and the third stage of theHuanghua Power Plant are studied by numerical model and physical model.The results show that the pres-ent inlet channel only satisfies the supply need of the first stage of the power plant.If the riverbed of the in-let reach is properly dredged,the need of water supply for the third stage of the power plant could be met.
In this paper the water-taking characteristics of the first, the second and the third stage of the Huanghua Power Plant are studied by numerical model and physical model. The results show that the present inlet channel only satisfies the supply need of the first stage of the power plant. If the riverbed of the inlet reach is properly dredged, the need of water supply for the third stage of the power plant could be met.