摘要
本文采用数值模拟与物模试验相结合的研究方法,详细地研究了黄骅电厂一、二、三期工程的取水特性。结果表明,现有河道只能满足电厂一期工程的取水需求;若将现有河道进行适当开挖,可以满足电厂三期取水需要。
In this paper, the intaking water characteristics of Huanghua power station in Xuanhui river are studied by numerical simulation and physical model test. The result shows that the river can only meet the cooling water requirement of the first stage project. If the river bed is properly dredged, it can satisfy the need of cooling water for all projects .
出处
《海洋工程》
CSCD
1997年第4期34-43,共10页
The Ocean Engineering
关键词
物模试验
数值模拟
冷却水
潮汐河流
physical test numerial simulation cooling water tidal river