本文通过太钢尖山铁矿选矿厂区的强穷地基处理工程实践,对强夯施工中夹击工艺做进一步的探讨,在小于或等于3000kN·m的强夯施工中,主夯点采用隔行夯打,并取得了预期效果。
In this paper, the practice in foundation construction by intensive ramming in Concentration Plantarea of Jianshan Iron Mine,the ramming technology is discussed. Ramming every other row in less andequil to 3, 000 kN. m intensive ram construction in main ram area had achived the desired results.
出处
《中国矿业》
1994年第S1期182-183,共2页
China Mining Magazine
关键词
强夯
能级
隔行打
效果
Intensive ramming, Level of energy, Ramming every other row, Results