摘要
对110 kV内桥接线在实际运行操作中存在的问题进行分析,给出内桥接线一、二次设备配置的改进方案,使得内桥接线方案得到优化,进一步提高内桥接线在电网运行中安全可靠性。
Through the analysis of the problems in the operation of 110 kV internal bridge connection,a scheme of configuration improvement for primary and secondary equipments of the internal bridge connection is put forward so as to optimize the connection scheme and further enhance its safety and reliability in the operation of power grids.
出处
《浙江电力》
2011年第11期21-23,共3页
Zhejiang Electric Power
关键词
改进
内桥接线
设备配置
improvement
internal bridge connection
equipment configuration