百米尾气烟囱分段安装技术 被引量:1

Technology for 100 Meters Exhaust Gas Stack Section Sequence Installation
下载PDF
导出
摘要 在土库曼斯坦巴格德雷第一天然气处理厂建设中,需要现场制作安装大型尾气烟囱。单座烟囱高100m、质量162t。经过反复分析比较,确定了400t吊车分段提升正装、空中对接补衬的施工工艺。对关键施工技术,包括分段数和分段点的确定、吊耳和平衡梁的设置、空中补衬等进行了充分论证。对吊装受力进行了分析计算,吊装过程平稳受控,烟囱吊装质量良好。 In the first Turkmen Natural Gas Processing Plant Bagh Bradley construction, largescale gas chimneys were needed for field fabrication and installation. The single chimney height was 100 meters and weighing 162 tons, the construction process was divided into the segment linings, lifted by 400 tons crane and assembling as the chimney lifted. After repeated analysis and comparison, the key construction technology was determined, including the number of segments and sub-point determination, setting for hanging ears and balance beam, the fill lining, analysis of lifting force calculation, a smooth control of lifting process.
作者 董正军
出处 《石油化工设备》 CAS 2011年第6期70-73,共4页 Petro-Chemical Equipment
关键词 钢制烟囱 分段正装 空中补衬 受力分析 steel chimney segment installation air fill lining lifting force analysis
  • 相关文献

参考文献4

二级参考文献2

  • 1GYT-200型液压提升装置说明书.
  • 2阳西发电厂一期工程240/2×φ6.2m烟囱钢内筒施工图.

共引文献1

同被引文献13

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部