摘要
结合380 m3高炉长时间停炉后开炉的实际情况,通过科学的开炉准备和合理地制定开炉方案、确定开炉参数和及时调整高炉操作等措施,实现了高炉带风装料、全焦开炉、顺利达产达效。
Based the practical conditions after a long time of blow off,with measures: scientific preparation for blow on,reasonable blowing-on plan and parameters,adjusting operation of blast furnace in time and so on,it is realized to charge with blast,blow on with full coke,and smoothly reach the standard production in 380 m3 blast furnace.
出处
《河北冶金》
2011年第11期12-15,共4页
Hebei Metallurgy
关键词
高炉
开炉
达产
实践
blast furnace
blow on
reach production
practice