云广直流系统仅带小湾电厂孤岛运行的调试与分析 被引量:11

On-site Commissioning and Analysis on the Islanding Operation of Yunnan-Guangdong UHVDC System Supplied Only by Xiaowan Power Plant
下载PDF
导出
摘要 楚雄侧孤岛运行是云广直流输电系统的正常运行方式之一。介绍了云广直流仅带小湾电厂孤岛运行方式的调试项目,包括联网-孤岛运行方式转换试验、孤岛系统稳态运行以及运行过程中模拟故障或扰动的试验。基于该孤岛运行方式的现场调试,对系统的实际运行特性进行了分析,结果初步验证了云广直流孤岛运行方式的可行性。现场试验及分析为进一步开展后续孤岛运行方式调试打下了基础,并为系统处于这种孤岛方式时的实际运行提供指导。 Islanding operation at Chuxiong side is a normal operation mode for Yunnan ??Guangdong UHVDC transmission system.The paper describes the on-site commissioning tests of the system islanding operation as it is supplied only by Xiaowan Power Plant at Chuxiong side,including the tests of mode changing between AC/DC parallel operation and islanding operation,of steady state performance,and of dynamic performance with disturbances or faults occurred in islanding operation.Based on the testing results,the actual islanding system operation performance is analyzed,and it is proves that the system runs smoothly in the islanding operation mode.The tests and analysis provide a technical foundation for further on-site commissioning of the system islanding operation and a guidance for its actual operation as it being in such islanding operation mode.
出处 《南方电网技术》 2011年第5期1-6,共6页 Southern Power System Technology
关键词 特高压直流输电 孤岛运行 现场调试 UHVDC transmission islanding operation on-site commissioning
  • 相关文献

参考文献2

二级参考文献13

  • 1Siemens.Functional Performance Test of Guizhou-Guangdong±500kV DC Transmission Project. PTDH171/P-000088/EE4.920.AZL-0 . 2003
  • 2Siemens.Dynamic Performance Test of Guizhou-Guangdong±500kV DC Transmission Project. PTDH171/P-000088/EE5.910.AZ-0 . 2003
  • 3HONG Chao,RAO Hong,BERGMANN K,et al.An Advanced Real Time Simulation Tool for Dynamic Studies of China Southern HVDC/HVAC Hybrid Power System. The International confer-ence on Electrical Engineering2005 . 2005
  • 4HONG Chao,RAO Hong.Studies on HVDC Control and Protection System Tests and the Related Key Technologies. Proceedings of the Conference on Software Engineering Education . 2007
  • 5Real Time Digital Simulator System Information Manual of Yunnan-Guangdong Line±800kV DC Transmission Project. CSG/YG/EB2.952.CS-0 . 2009
  • 6System Tests for HVDC Installations. CIGRE WG14.12 . 1995
  • 7Siemens.Know-How Transfer for HVDC Control and Protection. . 2002
  • 8Specification of Dynamic/Functional Performance Test of Yunnan-Guangdong Line±800kV DC Transmission Project. CSG/YG/ED4.911.CS-0 . 2008
  • 9Functional/Dynamic Performance Test of Guizhou-Guangdong II Line±500kV DC Transmission Project. CSG/GG2/EE4.911.XS-0 . 2006
  • 10CSG Technology Research Center.Reactive Power Management[]..2008

共引文献33

同被引文献72

引证文献11

二级引证文献134

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部